This is a summary of all changes deployed to our production environment in the scope of this release.
Release Date
18th June 2022
Release Type
Category | Feature | Description | Resolution | Impact |
Improvement |
Order Settings |
Enterprise and professional tier buyers were limited to set Payment terms unique to each supplier ID This prevented buyers from having more than 1 Purchase Order Payment Term per supplier. | We enabled buyers to set payment terms against individual supplier IDs. | Enterprise and professional tier administrators and team managers can now set payment terms (with the exception of Metal Fixing Allowance) against individual supplier IDs. |
Improvement | Tether To Grid | Until now, Tether to grid jobs were only processed twice per day at 06:00 UTC & 18:00 UTC. | We updated the Hangfire job schedule and doubled the number of scheduled Tether To Grid processing jobs from 2 to 4 jobs. | Tether To Grid jobs will now process every 6 hours at 05:00 UTC, 11:00 UTC, 17:00 UTC and 23:00 UTC. |
Fix |
Running Lines > Cost Submission > Cost Analysis > Tether To Grid |
Vendors could not toggle the Tether To Grid option for 'raw materials, 'labour' or 'other' costs. | We updated the feature logic to prevent this issue. | Vendors can now continue to select the Tether To Grid options for their product cost types. |